Hong Kong-Zhuhai-Macao Bridge Port Artificial Island Substation Is Expected To Be Completed By The End Of November Put Into Operation

- Nov 02, 2017-


Into  the 110-kilovolt substation at the artificial island of Hong  Kong-Zhuhai Bridge, several testers are staring at the lights on the  instrument to debug, the side of the equipment are affixed to the  "charged" reminder note. Substation wall part of  the wall has been installed, at the construction site, the workers are  busy for the "substation" for the final decoration.

And  then less than a month, this bear the Hong Kong-Zhuhai-Macao Bridge and  the port of artificial island power supply important task of the  substation can be put into use. "110-kilovolt artificial  island substation civil construction into the finishing work, is waiting  for acceptance, is expected to be completed by the end of November put  into operation." Zhuhai Power Supply Bureau official said.

In  order to protect the reliability of the Hong Kong-Zhuhai-Macao Bridge  and the Island, the Zhuhai Power Supply Bureau used the technology of  "network equipment" for the first time in the substation construction,  so that the two power supplies were "alternate" and greatly reduced the  power failure risk. Upon completion, the substation can also achieve unattended operation, more intelligent.


Power Plant


110 kV substation equipment has been charged test

Power is one of the prerequisites for the opening of the Hong Kong-Zhuhai-Macao Bridge. Recently,  the author boarded the Hong Kong-Zhuhai-Macao Bridge port artificial  island, a stylish building attracts the eye, which is about to be put  into use Hong Kong-Zhuhai-Macao Bridge artificial bridge substation. "Hong Kong-Zhuhai-Macao Bridge and the port of the artificial island  of all electricity will be exported from here." Southern Power Grid,  Guangdong Zhuhai Power Supply Bureau, said Liu Ying, director of  infrastructure projects.

110  kilovolt artificial island power transmission project is the Hong  Kong-Zhuhai-Macao bridge supporting power project, located in the  Zhuhai-Macao port artificial northwest corner of the Zhuhai port  municipal supporting area, the main commitment to the artificial island  and Hong Kong-Zhuhai Bridge ontology project power supply tasks. "This project to improve the country and Guangdong, Hong Kong and  Macao integrated transport system and the highway network to provide  electricity to ensure sustainable development is of great significance."  Liu said.

In  view of the particularity of the Hong Kong-Zhuhai-Macao Bridge  Artificial Island and the extreme importance of the electricity  customers on the island, the artificial island has laid a 10-kilovolt  line grid to provide more powerful power supply protection for the  development, construction and development of artificial islands. Is one of the hub of the entire distribution network.

Hong  Kong-Zhuhai-Macao Bridge port artificial island substation opened at  the end of February this year, the current substation electrical  equipment has been installed and commissioned to complete the completion  of all lines of cable laying, is the road and facade construction,  construction into the final stage, is expected by the end of November  this year Can be completed and put into production.

"Project  put into operation, the Zhuhai-Macao port artificial island will form a  220-kilovolt Kyrgyzstan transformer substation to 110-kilovolt  artificial island substation, 220 kV Gongbei substation to 110 kV bridge  dedicated substation and 110 kV artificial island substation to 110 kV  bridge Dedicated station connected to a closed-loop circuit, and the Zhuhai  power grid network reliable connection. "Liu Ying introduced.

In  addition, as one of the distribution network project Hong  Kong-Zhuhai-Macao Bridge Zhuhai-Macao port artificial island 10 kV  switch station project was completed on September 28 this year, put into  operation. "Hong Kong-Zhuhai-Macao Bridge to be opened at the end of the  conditions, including power supply is essential to the basic factors,  artificial island power transmission project smoothly, as soon as the  bridge reached the conditions of traffic clearance to provide a strong  guarantee." Liu said.

Power Plant

New 6000 meters underground ditch "electric island"

"Power  transmission and transformation" is a system of engineering, in  addition to the hub as a "substation", also need to set up cable  channel. How to "get through" from the urban area to the artificial island of  the transmission channel to become the Zhuhai Power Supply Bureau need  to overcome one of the problems.

Through the summer Bay, Gongbei port and the city streets of Kyrgyzstan to extend the island line to the island. "As  the underground pipeline is complex, the ground building is dense, the  difficulty is greatly improved." Eventually, after a round of new  underground ditch 6240 meters, laying cable 7200 meters "underground  needle thread" project, by Gongbei substation and Kyrgyzstan transformer  substation 110 thousand The cable is on the island

Hong  Kong-Zhuhai-Macao Bridge is the "century project", high standards,  strict management, any construction units should be strictly in  accordance with the construction standards to operate. In  the process of introducing cables into artificial islands, the  engineers of Zhuhai Power Supply Bureau had encountered problems. "The construction of the bridge is only a 65 cm × 65 cm cable trench,  and is the planning department approved the only channel, the space can  not be arranged conventional cable intermediate connector.

To this end, Zhuhai Power Supply Bureau adopted the advanced "MMJ" cable head welding technology. "From the current application point of view, its technology is  reliable, stable operation, take up small space and other  characteristics, without increasing the transformation of the original  cable trench in the case, can effectively save space, so as to promote  the smooth development of the project." Liu said.

According  to reports, this technology directly to the two cables welded together,  eliminating the huge cable connector equipment involved, take up space  greatly reduced, successfully overcome the cable trench space is  limited. In addition, "MMJ connector technology" also has a low resistance,  high strength characteristics, can withstand the impact of fault current  and long-term high-current operation of the advantages and reduce  operational risk.

The first use of "network prepared by the vote" to improve power supply reliability

In  June this year, held the national annual power reliability index  conference, the Southern Power Grid Guangdong Zhuhai Power Supply  Bureau, the average power outage time is only 1.87 hours, power supply  reliability rate ranks first in the country. In order to better complete the important task of providing power for  the Hong Kong-Zhuhai-Macao Bridge, it is the top priority of this  project to try to improve the "reliability" of power supply.

According  to reports, 10 kV artificial island switch station from the island 110  kilovolt port substation and the island's 110-kilovolt artificial island  substation on both sides of the power supply, and each side of the  power supply by two pairs of cables to form a dual-loop power supply , To protect the 10 kV artificial island switch station with 4 loop power supply of high reliability.

Power Plant

At the same time, the Zhuhai Power Supply Bureau for the first time  using the "network prepared by the self" approach to solve the public  station and dedicated station 110 thousand dollars from the vote can not  meet the line N-1 problem.

"In  simple terms, the network prepared by the self-cast technology is the  two lines are spare, when a line is disconnected, there is another line  to protect the continuity of power supply, through the provision of  self-cast device to increase communication interface equipment, And  the dedicated station on both sides of the equipment from the  investment information sharing, so that the action logic to meet the  different modes of operation. "Liu Ying said that by taking the network  and information sharing and other management methods, the substation  will be more" intelligent " Can be used in unattended mode of operation.

According  to the Zhuhai-Macao port artificial island overall planning  requirements, the appearance of the substation also has a more modern,  stylish design. 110  kilovolt artificial island power transmission project construction  Innovation of the building style, the building facade design for the  curtain wall and aluminum slab plate match to show a more beautiful  overall architectural image. At present, the facade of the substation is making the final "make-up". Liu  Ying said, "According to the design, the blue and blue wavy stripes in  the substation on the facade to extend to go, as a floating in the sea  color satin, and Lingdingyang on the Hong Kong - Zhuhai - Macao Bridge  echo each other.